Software contract was not unconscionable

internetcases » cases 2024-05-08

Summary:

Software vendor sued its customer because the customer stopped paying the vendor during implementation. Customer filed a counterclaim asserting that the contract between the parties was unconscionable because, if enforced, it would provide a “gross disparity in the values exchanged.” In other words, customer would be required to pay, but vendor would not have to…

Link:

http://evan.law/2024/05/07/software-contract-was-not-unconscionable/

From feeds:

CLS / ROC » internetcases » cases

Tags:

breach

Authors:

Evan Brown

Date tagged:

05/08/2024, 05:29